Update on Renovation Works in the Leonardo Building

Infopoint infopoint at ictp.it
Wed Oct 21 10:42:18 CEST 2026



Dear ICTP Community,

Please be advised that major renovation and modernization works are 
actively progressing inside the Leonardo Building. These projects aim to 
deliver upgraded, more functional facilities while significantly 
improving energy efficiency and building safety.

Below is an overview of the ongoing and upcoming works, along with 
expected impacts on daily operations:


      1. Library Area

  *


              Scope of Work:Installation of new electrical and HVAC
          systems is underway. Next week, the installation of a new
          marble floor will begin.

  *


            Impact:Noise and dust in the area.


      2. Staircase Access

  *


              Scope of Work:Demolition work is complete. Civil works
          will take place around the staircase to install a new door
          between the Math corridor and the staircase, as well as to
          create the new main entrance to the Library.

  *


            Impact:The staircase will remain open and accessible during
          these works, but there will be significant noise and dust.


      3. In Front of Office LB-115

  *


              Scope of Work:Work will begin in front of office LB-115 to
          construct a new technical space and a dedicated locker area.
          This zone will be securely partitioned, and corridor access to
          the stairs will remain open.

  *


            Impact:The corridor will remain open and accessible during
          these works, but there will be significant noise and dust.


      4. Office LB-115

  *


              Scope of Work:Demolition work is complete. Civil works
          will take place to install a new dividing wall between office
          LB-115 and the Library, along with a new entrance door.

  *


            Impact:Office LB-115 will be available again in the second
          half of November 2026.


      5. Second Floor – Oppenheimer Area Restrooms & Office LB-269A
      (Asbestos Removal)

  *


              Scope of Work: Removal of asbestos materials in the
          restrooms adjacent to the Oppenheimer Room is underway. This
          is required to connect the main air ducts between the Library
          and the roof. The removal of asbestos is being conducted by a
          specialist company in strict compliance with safety regulations.

  *


            Impact:The restrooms in this area will be completely closed.
          Users may use the restrooms in the HE Section. Office LB-269A
          is subject to the same closure. The exact reopening date
          depends on statutory inspections and clearances from local
          regulatory authorities; works are expected to finish within 20
          days. Expect noise in the area.


      6. Windows & Exterior Façade Renovation

  *


              Scope of Work:

       o


                Scaffolding:Erected on the west corner of the building,
              spanning from ground level to the roof. Window restoration
              is underway.

      o


                Window Replacement:High-efficiency, safety-upgraded
              windows will be installed in the original seaside wing.
              The initial phase covers the Library windows and
              second-floor rooms (Oppenheimer Room, LB-232, LB-233, and
              LB-236).

      o


                Façade Repair:Repairs to the concrete elements of the
              exterior façade will take place concurrently to secure the
              structure and prevent falling debris.

  *


            Impact:The Dirac stairs, the terrace, and all other passage
          routes will remain open and fully secured for safe pedestrian
          traffic throughout this phase.


      7. Roof Works

  *


              Scope of Work:Works will start soon to construct a
          dedicated rooftop technical zone. This will accommodate the
          new Air Handling Units (AHUs) serving the renovated Library.

  *


            Impact:Following asbestos removal, the women’s restrooms in
          the CM and HE Sections will remain closed to create a passage
          route from the Library to the roof. During this period, one
          men’s restroom will be designated for women. Works are
          scheduled to complete in January 2027. Expect noise and dust
          in the area.


      8. New Air-Conditioning Pipelines (Second Floor)

  *


              Scope of Work:To replace rusted piping and restore the
          original layout, we are relocating the pipes that supply hot
          and cold water for the second-floor air-conditioning system.

  *


            Impact:System integration and connections will require
          temporary heating/cooling outages in specific areas. Works are
          currently underway and will continue throughout November 2026.
          Expect noise and dust in the area.


  *
    *Affected Areas:*

*
*

  *
    *CM Section:*
    **/Offices LB-227, LB-230, LB-231, LB-232, LB-233, LB-234, LB-235,
    and LB-236:/ Disruption of heating. Portable electric heaters will
    be provided. Central heating will be restored during November 2026.
    Expect noise in the area.

*
*

  *
    *Directorate / HE Area:*
    /Offices LB-275, LB-276, LB-281, and LB-282:/ Disruption of heating.
    Portable electric heaters will be provided. Central heating will be
    restored in December 2026.
    /Offices LB-268, LB-270, LB-276, LB-278, and LB-281:/ Wall
    restoration will take place this week and next week. Expect noise
    and dust in the area.

*
*

  *
    *Math Corridor Area:*
  *
    **/Offices LB-113, LB-114, and LB-115:/ Disruption of heating.
    Portable electric heaters will be provided. Expect noise in the area.
  *
    /Office LB-115:/ Room will be available again in the second half of
    November 2026. Expect noise and dust in the area.



      _What to Expect & Safety Precautions_

We are fully aware that these activities will generate significant noise 
and dust in certain areas of the building. We ask for your patience and 
understanding as we work through these necessary phases to deliver a 
modernized, comfortable, and energy-efficient building.  Alternative 
shared workspaces are available in the Galileo - please approach 
infopoint for more information.

    - Please pay close attention to safety signage and temporary barriers.
    - Do not enter clearly marked work zones.

Thank you for your cooperation and support.

Facilities Management Office

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.ictp.it/pipermail/ictp-announcements/attachments/20261021/8a51941c/attachment-0001.htm>


More information about the Ictp-announcements mailing list