Update on Renovation Works in the Leonardo Building
Infopoint
infopoint at ictp.it
Wed Oct 21 10:42:18 CEST 2026
Dear ICTP Community,
Please be advised that major renovation and modernization works are
actively progressing inside the Leonardo Building. These projects aim to
deliver upgraded, more functional facilities while significantly
improving energy efficiency and building safety.
Below is an overview of the ongoing and upcoming works, along with
expected impacts on daily operations:
1. Library Area
*
Scope of Work:Installation of new electrical and HVAC
systems is underway. Next week, the installation of a new
marble floor will begin.
*
Impact:Noise and dust in the area.
2. Staircase Access
*
Scope of Work:Demolition work is complete. Civil works
will take place around the staircase to install a new door
between the Math corridor and the staircase, as well as to
create the new main entrance to the Library.
*
Impact:The staircase will remain open and accessible during
these works, but there will be significant noise and dust.
3. In Front of Office LB-115
*
Scope of Work:Work will begin in front of office LB-115 to
construct a new technical space and a dedicated locker area.
This zone will be securely partitioned, and corridor access to
the stairs will remain open.
*
Impact:The corridor will remain open and accessible during
these works, but there will be significant noise and dust.
4. Office LB-115
*
Scope of Work:Demolition work is complete. Civil works
will take place to install a new dividing wall between office
LB-115 and the Library, along with a new entrance door.
*
Impact:Office LB-115 will be available again in the second
half of November 2026.
5. Second Floor – Oppenheimer Area Restrooms & Office LB-269A
(Asbestos Removal)
*
Scope of Work: Removal of asbestos materials in the
restrooms adjacent to the Oppenheimer Room is underway. This
is required to connect the main air ducts between the Library
and the roof. The removal of asbestos is being conducted by a
specialist company in strict compliance with safety regulations.
*
Impact:The restrooms in this area will be completely closed.
Users may use the restrooms in the HE Section. Office LB-269A
is subject to the same closure. The exact reopening date
depends on statutory inspections and clearances from local
regulatory authorities; works are expected to finish within 20
days. Expect noise in the area.
6. Windows & Exterior Façade Renovation
*
Scope of Work:
o
Scaffolding:Erected on the west corner of the building,
spanning from ground level to the roof. Window restoration
is underway.
o
Window Replacement:High-efficiency, safety-upgraded
windows will be installed in the original seaside wing.
The initial phase covers the Library windows and
second-floor rooms (Oppenheimer Room, LB-232, LB-233, and
LB-236).
o
Façade Repair:Repairs to the concrete elements of the
exterior façade will take place concurrently to secure the
structure and prevent falling debris.
*
Impact:The Dirac stairs, the terrace, and all other passage
routes will remain open and fully secured for safe pedestrian
traffic throughout this phase.
7. Roof Works
*
Scope of Work:Works will start soon to construct a
dedicated rooftop technical zone. This will accommodate the
new Air Handling Units (AHUs) serving the renovated Library.
*
Impact:Following asbestos removal, the women’s restrooms in
the CM and HE Sections will remain closed to create a passage
route from the Library to the roof. During this period, one
men’s restroom will be designated for women. Works are
scheduled to complete in January 2027. Expect noise and dust
in the area.
8. New Air-Conditioning Pipelines (Second Floor)
*
Scope of Work:To replace rusted piping and restore the
original layout, we are relocating the pipes that supply hot
and cold water for the second-floor air-conditioning system.
*
Impact:System integration and connections will require
temporary heating/cooling outages in specific areas. Works are
currently underway and will continue throughout November 2026.
Expect noise and dust in the area.
*
*Affected Areas:*
*
*
*
*CM Section:*
**/Offices LB-227, LB-230, LB-231, LB-232, LB-233, LB-234, LB-235,
and LB-236:/ Disruption of heating. Portable electric heaters will
be provided. Central heating will be restored during November 2026.
Expect noise in the area.
*
*
*
*Directorate / HE Area:*
/Offices LB-275, LB-276, LB-281, and LB-282:/ Disruption of heating.
Portable electric heaters will be provided. Central heating will be
restored in December 2026.
/Offices LB-268, LB-270, LB-276, LB-278, and LB-281:/ Wall
restoration will take place this week and next week. Expect noise
and dust in the area.
*
*
*
*Math Corridor Area:*
*
**/Offices LB-113, LB-114, and LB-115:/ Disruption of heating.
Portable electric heaters will be provided. Expect noise in the area.
*
/Office LB-115:/ Room will be available again in the second half of
November 2026. Expect noise and dust in the area.
_What to Expect & Safety Precautions_
We are fully aware that these activities will generate significant noise
and dust in certain areas of the building. We ask for your patience and
understanding as we work through these necessary phases to deliver a
modernized, comfortable, and energy-efficient building. Alternative
shared workspaces are available in the Galileo - please approach
infopoint for more information.
- Please pay close attention to safety signage and temporary barriers.
- Do not enter clearly marked work zones.
Thank you for your cooperation and support.
Facilities Management Office
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.ictp.it/pipermail/ictp-announcements/attachments/20261021/8a51941c/attachment-0001.htm>
More information about the Ictp-announcements
mailing list